The Scheduler gives Build & Operate a Gantt-style plan of your work. On the web, every project you have access to sits on one timeline, so you can see where each job stands without opening projects one at a time. Plan tasks with dates and finish-to-start links, assign crews and equipment as resources, spot a crew that is booked twice, and see right away how a change moves a project's end date. Field teams can view the schedule, read-only, in the STACK Field App.
NOTE
The Scheduler is a planning tool, not an auto-scheduling engine. You place and link tasks, and the Scheduler shows the result. It does not move linked tasks, optimize dates or level resources for you.
Key Information
- Pro feature: the Scheduler is part of STACK | Build & Operate Pro. It is on during a Pro trial. If your organization does not have it, the menu shows a PRO badge. Contact build-support@stackct.com to turn it on.
- Who can use it: Admins and above can view and edit the schedule. Power Collaborators can view it only. Lower roles do not have access.
- Edit on the web, view on mobile: scheduling data is created and edited in the web portal. The STACK Field App shows the schedule read-only.
- Resources do not use a seat: crews, equipment, vehicles and other resources are not tied to user accounts, so creating one does not use a license.
- Time zones: the timeline is drawn in your own time zone, so tasks in projects in other time zones appear at their real moment in your local time.
View All Your Projects on One Timeline
The Schedule tab lists one row per project, with its groups, tasks and milestones underneath. The grid on the left shows Name, Resources, Start, End and Days, and the timeline on the right shows each task as a bar.
- In the left menu, under Organization Info, click Scheduler.
- Click the arrow next to a project or group to expand or collapse it.
- Use All Projects to show only selected projects, All Resources to show only the tasks a resource is on, and the search box to find tasks, resources or projects by name. Click Clear filters to show everything again.
- Click the Columns icon at the right end of the grid header to choose which columns to show.
TIP
Projects you can only view appear as muted, read-only rows. You can still see their dates and tasks, but you cannot change them.
Add Groups, Tasks, and Milestones
- Click the three dots (Actions) at the end of a project or group row, or right-click the row.
- Choose Add group inside, Add task inside, or Add milestone inside. On a task row, the same menu offers Add group below, Add task below, and Add milestone below.
- Type a name for the new row and press Enter. A new task lasts one day and starts on its group's start date.
- To move a task, drag its bar along the timeline. To change its length, drag either end of the bar.
- To rename or remove a row, open its three-dot menu and choose Rename or Delete.
NOTE
A project's row shows the span of its scheduled work. The project's planned Start Date and End Date are set in the project's Settings, on the General tab.
Link Tasks with Dependencies
Link two tasks with a finish-to-start dependency when one task cannot start until another one finishes.
- Hover over the first task's bar. A small dot appears at each end.
- Drag from the dot at the end of the bar to the task that depends on it. An arrow now connects the two bars.
If a task ends after a linked task is due to start, the Scheduler does not move the later task for you. The link between them turns orange so you can see the problem and move the later task yourself.
IMPORTANT
When a project's scheduled work runs past its planned end date, the project is flagged as late.
Plan Crews and Equipment as Resources
Resources are free-form: crews, equipment, vehicles, or anything else you schedule. Manage them on the Resources tab.
- On the Resources tab, click Create Resource.
- Enter a Name, a Type (for example, Crew, Equipment, or Vehicle), and an optional Group, then click Create.
- Use the Type and Group filters or the search box to find resources, and Bulk Actions to work with several at once.
To assign resources to a task:
- On the Schedule tab, open the task's three-dot menu and choose Edit resources.
- Check each resource you want on the task. You can also type in Search or add new resource to find one or create it on the spot.
- Click Apply. The resources appear in the task's Resources column and on its bar.
Find Double-Booked Resources
When the same resource is booked on tasks that overlap, the Scheduler shows the resource name in red with an alert icon on those tasks, and a count appears on the Overbooked button.
- Click Overbooked to show only the tasks with a double-booked resource.
- Move one of the tasks, or change its resources, so the bookings no longer overlap. The alert clears as soon as the clash is gone.
- Click Clear filters to see the whole schedule again.
Save, Discard, and Resolve Changes
- While you edit, Unsaved changes appears at the bottom of the page. Your changes are not stored until you click Save. Other users in your organization see them the next time they load the Scheduler.
- Click Discard changes to drop every unsaved edit. You are asked to confirm first, and you see the same confirmation if you leave the Scheduler with unsaved work.
- Click Refresh to load the latest saved schedule.
- If someone else saved a change to the same item while you were editing, a conflict panel lets you choose whether to keep your version or theirs, one item at a time or all at once.
Review Schedule History
The History tab lists every saved change to the schedule, newest first: what changed, the project, the date, and who made the change. Use All Projects to show the history of selected projects only.
View the Schedule in the STACK Field App
Field teams can check the schedule from the STACK Field App on iOS, Android, and the Windows desktop app. The schedule is read-only on mobile: there are no edit controls.
- A phone shows one week at a time, with a jump-to-date control. A tablet shows four weeks, and the Windows desktop app shows five.
- Milestones appear as dated divider rows among the task cards.
- Changes made on the web appear in the app after it syncs.
- The schedule is available offline, from the data last synced to the device.
- The schedule menu appears for Power Collaborators and above.